Stay in the know

NEIGHBORHOOD NEWS

  • The Arrowhead Landscaping Committee has completed several projects in 2024 and has outlined a few projects for 2025.

    2024 Projects

    • 19 Interior locations were identified for landscape updates, including street intersections, cul-de-sacs and gates. 

      • The new look is made up of new perennial plantings and, where possible, the Arrowhead signature tree – Hot Wings Maple. 

    • One Arrowhead Place adopted and completed a similar landscape renovation plan.

    • Several other Associations in Arrowhead are considering similar landscape renovations.

    • Roundabout landscaping

      • Center Island – upon completion of the roundabout asphalt, installation of spruce trees and a Monument and sign identifying Arrowhead will begin.

      • The remainder of the landscaping for the center island and the area along Hwy 6 will be completed in spring and summer 2025 when the weather is more conducive for successful planting.

    •  Annual holiday tree lighting.


    2025 Projects

    • Completion of the 19 interior locations that were identified and started in 2024.

    • Renovation and updating of the main gate entrance/exit landscaping from Hwy 6 to the Main Gatehouse (after the AMD entrance/exit widening project is complete).

    • Roundabout landscaping – the center island and the area along Hwy 6 will be completed in spring and summer 2025 when the weather is more conducive for successful planting.

  • Update & plan for completion (assuming good weather & asphalt availability)

    Week of 10/14/2024 Review

    • 10/15/2024 - Signage install starts, will take a week

    • 10/16/2024 - Striping/painting starts

    • 10/18/2024 - Hydroseeding

    Week of 10/21/2024

    • 10/22/2024 - Complete striping (3-way arrow is not in stock and is backordered)

    • 10/24/2024 - Final inspection with CDOT, Kumar, SGM, AEI, AMD

    Bus Stop Shelters are fabricated but are waiting for the rooftop solar panels so there is no ship date yet.

  • In addition to building the roundabout, the main gate entrance and exit lanes will be widened from Highway 6 to the Main Gatehouse. This will allow for 2 full entrance lanes on the entrance side, and a dedicated pedestrian lane on the exit side.  

    Visit the Highway 6 Safe Crossing Project webpage HERE for additional information on this project.

  • Eagle River Water & Sanitation District (ERWSD) water main replacement  Late April 2024 - June 2025 (with work suspended during winter months).  The ERWSD is replacing a critical, aging, water main in the Arrowhead ski area, along Piece-O-Cake ski run and Cresta Road. 

    Plan Update

    • Week of September 2 – Continue trenching for the second pipe segment.

    • Week of September 9 – Continue trenching for the second pipe segment.

    • Week of September 16 – Install water main for the second pipe segment. Restore tie-in area.

    • Week of September 23 – Testing of second pipe segment and begin restoration.

    • The project will break for winter and resume in 2025. The roadway crossing, creek crossing and valve vault will be completed in 2025.

    Click HERE to see a picture of the project pipe segments

    Click HERE for the detailed letter from ERWSD. For additional project updates visit erwsd.org.

  • The Arrowhead Association Board of Directors held a Town Hall for Arrowhead property owners on August 9, 2024, at 3:00 p.m. (MDT). A link to view the meeting presentation and the recording will be available here soon.

    The meeting was part of the continuing effort to keep homeowners informed of what the Association has been working on this year in its continuing efforts to establish Arrowhead as the "Most Desirable Luxury On-Mountain Resort Community in the Vail Valley."

    Click HERE to view a pdf of the presentation

  • The ERWSD construction project (above) impacts the original Lower Apache Trail route. In an effort to keep the Apache trail open this summer, the ERWSD, Vail Resorts and Arrowhead approved Vail Valley Mountain Trails Alliance's (VVMTA) proposal and plan to build a new Apache Trail Extension, connecting to the Ute Trail.

    VVMTA and volunteers worked diligently building the new Apache Trail Extension. Click HERE to see a picture of the new trail extension.

  • Arrowhead Association has a multi-year vision to enhance the recreational and leisure experience for the community and its guests. A component of this is to help activate the Arrowhead Plaza for special events and informal gatherings.

    The projects planned for completion in 2024 are:

    1. COMPLETED - New railings on the bridge at the arrival plaza, to open the beautiful view of the creek. Click HERE to see a picture of the new railings.

    2. COMPLETED -Create a better access path behind Blinky’s, leading to the ski area base/lawn area/hiking trails. 

    3. COMPLETED - Hillside erosion control 

    4. Create a McCoy Creek path/trail

    Click HERE for a map of the project areas.

  • Arrowhead has installed soundproofing at the pickleball courts.

    Arrowhead created a new pickleball court social area just outside of the West gate at the courts. The area is a 16’ x 32’ wood deck that is level with the courts. Click HERE to see a picture of the new deck.

    The Main Gatehouse and the Racquet Sports Center roofs were replaced this May as well.

  • In 2024, the Arrowhead Metro District completed wildfire fuel reduction on an additional 223.5 acres of land surrounding Arrowhead with partners, Eagle Valley Wildland and the Eagle River Fire District.  This was the goal for the year, and brings the total number of acres mitigated to 375 acres.  To Arrowhead’s immediate west there are 140 remaining acres of land that the Metro District feels must be mitigated for wildfires by dramatically reducing fuel loads, and they are committed to finishing that piece in 2025.  It is possible that the Edwards Metro District and the Homestead Homeowners Association may participate financially in that last remaining piece, but rest assured that the work will be supported by the Arrowhead Metro District whether they do or not.

  • The Arrowhead Association held a virtual Annual Meeting of Members on December 26, 2023, at 3:00 p.m. (MST).

    To view a recording of the Annual Meeting, click HERE. Use passcode: sJ6+N.3e

    You may access the Annual Meeting presentation HERE.

    Click HERE for the At-Large Annual Meeting Materials.

    Click HERE for the High-Density Annual Meeting Materials.

  • The Arrowhead Association Board of Directors held a Town Hall meeting for Arrowhead property owners on October 23, 2023, at 3:00 p.m. (MDT). The meeting was conducted in person at Broken Arrow and via Zoom.

    Click HERE for a copy of the Town Hall presentation.

    Click HERE and use the passcode 4!#c%T1v to access the recording of the Town Hall meeting.

  • The Arrowhead Association Board of Directors held a virtual Town Hall for Arrowhead property owners on July 20, 2023, at 3:00 p.m. (MDT). The meeting was conducted via Zoom.

    The meeting was part of our continuing effort to keep homeowners informed of what the Association has been working on this year in its continuing efforts to establish Arrowhead as the "Most Desirable Luxury On-Mountain Resort Community in the Vail Valley."

    Click HERE for a copy of the Town Hall Presentation.

    Click HERE and use the passcode #qq1yjYP to access the recording of the Town Hall meeting.

  • The objectives of the 2023 Arrowhead Homeowners Survey were:

    -Support the Arrowhead vision of being the most desirable luxury, on-mountain resort community in the Vail Valley.

    • Support the Arrowhead vision of being the most desirable luxury, on-mountain resort community in the Vail Valley.

    • Provide clear and specific direction to the Arrowhead Board.

    • Reflect the opinions of our residents in the survey and identify the areas where the Board should focus our resources and energy.

    • Click HERE to see the Survey Results Summary.

  • The Arrowhead Association is pleased to announce progress in the long-term challenge of the gate access system. Now available to Arrowhead Homeowners is Bluetooth-enabled entry and remote gate unlock capabilities through a smartphone app – ProdataKey (pdk).

    Click HERE for additional information.

    Click HERE for the ProdataKey Enrollment Form.

    Use of this app for entry into Arrowhead is available to verified Homeowners ONLY.

  • Follow us (or give us a “Like”) on Facebook – @Arrowhead

    Follow us on Instagram – @arrowheadco

    When sharing photos on your personal social media accounts, tag us with #ThisisArrowhead